NEW QUESTION 62
Which of the following statements is CORRECT?

  • A. The higher the correlation, the better the regression estimate.
  • B. The lower the correlation, the greater the likelihood that homoscedasticity exists with respect to thepredicted variable.
  • C. Regression estimates are better made with positive correlation than with negative correlation.
  • D. The better the regression estimate, the greater the likelihood that homoscedasticity exists with therespect to the predicted variable.

Answer: A

 

NEW QUESTION 63
Which of the following are likely to be positive actions in obtaining a supplier's commitment to quality improvement?
. Involving the supplier early in the product development stage. . Partially reimbursing the supplier, when the product is rejected. . Establishing a firm schedule of required product quantities and dates. . Providing meaningful and timely quality performance feedback.

  • A. I,IIIandIVonly
  • B. I,II,IIIandIV
  • C. I,IIandIVonly
  • D. IandIVonly

Answer: A

 

NEW QUESTION 64
A process is in control with a defect rate of 0.2%. A sampling plans calls for 30 items to be selected at random, and for the process to be shut down and corrected if any defects are found. How often will the process be shut down without a change in the defect rate?

  • A. None of the above
  • B. 1.22% of the time
  • C. 5.83% of the time
  • D. 3.91% of the time

Answer: C

 

NEW QUESTION 65
Which of the following tools can provide a ranking of things to be done?

  • A. Scatter diagram.
  • B. Measles charts.
  • C. Cause & effect diagram.
  • D. Checklist.

Answer: D

 

NEW QUESTION 66
Writing and establishing process control procedures is

  • A. Preventive action.
  • B. Corrective action.
  • C. Disposition.
  • D. Notification.

Answer: A

 

NEW QUESTION 67
An audit will be viewed as a constructive service to the function which is audited when it

  • A. Furnishes enough detailed facts so the necessary action can be determined.
  • B. Proposes corrective action for each item uncovered.
  • C. Is conducted by nontechnical auditors.
  • D. Is general enough to permit managerial intervention.

Answer: A

 

NEW QUESTION 68
The audit team normally advises the auditee immediately upon the discovery of a finding during an audit.
Which of the following items is (are) valid reasons for taking this action?
I. If corrected immediately, the findings may be eliminated from the audit report.
II. If corrected immediately, it shows genuine auditee interest in the objectives of the audit.
III. If corrected immediately, it demonstrates the strength of an ongoing audit program.

  • A. I, II and III
  • B. I only
  • C. III only
  • D. II and III only

Answer: D

 

NEW QUESTION 69
A comprehensive corrective action program is initiated at a large company. Input for CARs are received from customers, internal and external audits, material review reports and other sources. Which two of the following groups would usually administer and control the CAR process?
I. Management review team.
II. Quality department.
III. Corrective Action Board.
IV. Material Review Board.

  • A. II and III only
  • B. I and II only
  • C. I and III only
  • D. III and IV only

Answer: C

 

NEW QUESTION 70
Which of the following list of basic NDT techniques are X ray types?

  • A. Ultrasonic / Optical.
  • B. Radiation / Image generation.
  • C. Electromagnetic / Thermal.
  • D. Thermal / Radiation.

Answer: B

 

NEW QUESTION 71
When using a control chart, a point plotting within the limits on the chart is

  • A. The equivalent of not rejecting the hypothesis that the process is in control.
  • B. The equivalent of type II error.
  • C. The equivalent of accepting the hypothesis that the process is in control.
  • D. The equivalent of type I error.

Answer: A

Explanation:
Explanation/Reference:

 

NEW QUESTION 72
The Shewhart or Deming cycle is often referred to as

  • A. Problem solving flow chart.
  • B. Plan-do-check-act.
  • C. The affinity diagram.
  • D. The cause and effect diagram.

Answer: B

 

NEW QUESTION 73
The descriptive name for a fishbone or Ishikawa diagram is which of the following?

  • A. Scatter diagram.
  • B. Flow charts.
  • C. Pareto diagram.
  • D. Cause and effect diagrams.

Answer: D

 

NEW QUESTION 74
A pre-award evaluation of a supplier's quality system capability should NOT include consideration of

  • A. The supplier's geographical location.
  • B. The supplier's product-quality history.
  • C. The supplier's implementation of quality manual procedures.
  • D. The supplier's skills in quality control techniques.

Answer: A

 

NEW QUESTION 75
Which of the following quality gurus was very critical of merit-pay and individual bonuses?
He discouraged management by objectives and the ranking of employees by performance.

  • A. Dr. Taguchi
  • B. Dr. Deming
  • C. Dr. Feigenbaum
  • D. Dr. Juran

Answer: B

 

NEW QUESTION 76
A pre-award evaluation of a supplier's quality system capability should NOT include consideration of

  • A. The supplier's geographical location.
  • B. The supplier's product-quality history.
  • C. The supplier's implementation of quality manual procedures.
  • D. The supplier's skills in quality control techniques.

Answer: A

 

NEW QUESTION 77
Failure mode, effect, and criticality analysis, (FMECA) is primarily for the purpose of

  • A. Learning as much about the item as possible after qualification test.
  • B. Determining the cause of a failure, by dissecting the item, to help obtain corrective action.
  • C. Determining the way an item will most likely fail to help obtain design and procedural safeguardsagainst such failures.
  • D. Determining, by extensive analysis, the reliability of an item.

Answer: C

 

NEW QUESTION 78
Determine the coefficient of variation for the last 500 pilot plant test runs of high temperature film having a mean of 900 Kelvin with a standard deviation of 54.

  • A. 6%
  • B. 16.7%
  • C. 31%
  • D. 6%

Answer: A

 

NEW QUESTION 79
......